Item 14 - Williamson Creek Wastewater Interceptor Project Presentation — original pdf
Backup
Williamson Creek Wastewater Interceptor Project Kane Wei, P.E. Austin Water Supervising Engineer Water & Wastewater Commission January 14, 2026 Agenda Agenda Project Overview Routing Requirements Neighborhood Partnership Parks and Recreation Partnership Watershed Protection Partnership Summary 2 Project Overview 18,800+ linear feet of 72-inch diameter gravity wastewater interceptor installed using a two-pass tunneling method Project drivers: increase capacity replace aging infrastructure reduce the potential for future sanitary sewer overflows to protect the environment 3 Existing Interceptor Requires Replacement Built in the early 1960’s – size, age, location, and condition of the existing pipelines make it susceptible to infiltration during rain events, which may result in overflows No existing odor control along interceptor 4 Major Project Components Excavation of 18,800 LF of tunnel, ranging from 20 to 90 ft below grade, entirely outside of the Erosion Hazard Zone. Installation of 18,600 LF of 72-inch and 200 LF of 84-inch corrosion resistant fiberglass pipe with grouted annulus. 6 Operations and Maintenance (O&M) Shafts. 11 connection shafts for connections with the new tunnel All shafts are made of corrosion resistant fiberglass or polymer concrete materials 5 Project Benefits Installation of 22 local pipeline reconnections via open cut (5,400 LF of 8” to 48”) and jack and bore (2,500 LF of 12” to 54”) construction methods Removal and abandonment of existing wastewater pipelines and manholes in the creek. New biological odor control facility and associated rain gardens designed for potential future trailhead parking lot. Cured-in-Place (CIPP) pipeline rehabilitation of 2,700 LF of existing 36” diameter concrete pipe. Extensive environmental site restoration (native seeding, tree plantings, etc). 6 Why was this route selected? 18 different alignments evaluated via scoring matrix 22 environmental constraints considered 7 7 8 Neighborhood Partnership: Community Benefits In 2017 and 2024 - Community Open Houses in Districts 2 and 3 Increasing parkland and future trails Coordinated with nearby public projects (storm improvements, trails, etc). Additional public meetings in 2026+ 9 Parks and Recreation Partnership: Expanding Greenbelt and Trails Access 1 acre of acquired sidewalk, trail, and recreation easements 3 acres of acquired properties necessary for temporary workspace areas, to be transferred after construction is completed Transfer of up to 59.6 acres for future trailhead access near Jimmy Clay Golf Course Total: over 63 acres of additional parkland, approved through Parks Board 10 Parks and Recreation Partnership: Odor Control and Trailhead Access Odor control facility to reduce odors Rain gardens were oversized to accommodate future potential trail head parking and access Concrete paved access instead of gravel 11 Watershed Protection Partnership: Creek Restoration Proper abandonment and removal of pipe and manholes in the creek Each location individually evaluated with Watershed Protection for the least environmental impact and most creek stabilization 12 Watershed Protection Partnership: Flood Reduction Removal of abandoned structure and “hill” to lower the bed of the creek to match its surrounds Increases conveyance ability and reduces flood risk of Williamson Creek Approved through both Planning Commission and Environmental Commission 13 Watershed Protection Partnership: Environmental Mats for Temporary Access Laid down with minimal disturbance to the underlying soil, then picked up with less mitigation required. Used where feasible. Incorporated via feedback from community 14 Where are we now? 2016 to 2019 – Preliminary Engineering Phase 2019 to 2023 – Detailed Design Phase 2023 to 2025 – Permitting and Easement Acquisition September 18, 2024 – Environmental Commission November 25, 2024 – Parks and Recreation Board May 13, 2025 – Planning Commission 2025 – Advertisement January 14, 2026 – Water and Wastewater Commission January 22, 2026 – Council Meeting 2026 to 2031 – Construction Phase 15 Project Website www.austintexas.gov/wci Project details, maps, exhibits Past presentations Sign up for email updates 16 Building Austin’s water future, together. Water & Wastewater Commission January 14, 2026