Water and Wastewater CommissionJune 8, 2022

E4 — original pdf

Backup
Thumbnail of the first page of the PDF
Page 1 of 6 pages

After Action Status Update Water & Wastewater Commission | June 8, 2022 Overview  Winter Storm Uri Improvements Plan • 79 Improvements Identified • 68 Completed  Ullrich Turbidity Event Improvements Plan • 38 Improvements Identified • 30 Completed  Of 17 remaining improvements, 14 are longer-term CIP initiatives 2 Recently Completed Resiliency Improvements  Operations Staffing, Procedures and Training • Added access for management staff to monitor SCADA remotely • Enabled external notification of turbidity exceedance alarms • Enabled automatic backwashing of filters for turbidity trigger  Infrastructure Enhancements • Completed Davis Water Treatment Plant Power Distribution Upgrade • Added third electrical feed to Ullrich Water Treatment Plant and enabled automatic switching capability  Internal / External Communications • Provided emergency notifications using My ATX Water customer portal and Warn Central Texas • Provided regular incident status updates to Austin Water staff 3 Resiliency Improvements Underway (to be completed by September 30, 2022)  Operations Staffing, Procedures and Training • New Operations and Training positions: recruitment process underway criteria • Define and implement operational situational awareness  Infrastructure Enhancements • Replacement of North Austin Reservoir • Complete winterization of components at plants • Review SCADA alarms, seeding alert pop-ups, modernization opportunities  Emergency Preparedness • • 4 Implement Emergency Preparedness Plan to meet SB3 requirements Increase Incident Management Team Roster and conduct annual training activities Longer Term Resiliency Improvements  Automatic shutdown of filters for turbidity exceedances  Water storage and transmission projects in the distribution system  Electric generation and power resiliency projects at treatment plants, lift stations and pump stations  Improved chemical storage and sludge storage/disposal capabilities at treatment plants  Installation of My ATX Water (AMI) meters 5 Questions / Discussion