Historic Landmark CommissionOct. 8, 2025

6.1 - 6th St Presentation — original pdf

Backup
Thumbnail of the first page of the PDF
Page 1 of 11 pages

Sixth Street Preliminary Engineering Report (PER) Architectural Review Committee Meeting October 8, 2025 Transportation and Public Works Recap of 6th Street PER • Study Area: 6th Street (IH-35 to Congress Avenue). • Purpose: Identify transportation and mobility improvements to form the long-term vision for the street. • Goal: Develop a set (1) of recommended improvements with their associated costs. • ACT Plan: 3 Options. • Schedule: Conclude PER by end of 2025; begin design in 2026; construction in 2027, pending 2026 Bond Election. • Completed to Date: Survey, Subsurface Utility Exploration, Preliminary Layout of Options Project Limits Map Alternative 1 Alternative 1 Alternative 2 Alternative 2 Alternative 3 Alternative 3 Comparison Matrix Next Steps *Stakeholder meeting #1 occurred in June 2025. THANK YOU!