Backup

Burnet MS -Project Schedule Overview 5 2 0 2 6 2 0 2 7 2 0 2 8 2 0 2 NEW BUILDING CONSTRUCTION Permit Spring 2025 Construction Start Q3 2025 Start Move-In Q2 2027 School Opening August 2027 DESIGN DD Aug 2024 CD Mar 2025 EXISTING BUILDING DEMO & SITEWORK (Proposed dates are subject to change) Demo Summer 2027 Site work Complete Q2 2028 1