Item 3. Update on the Phase 2 Construction Project — original pdf
Backup
EMMA S. BARRIENTOS MEXICAN AMERICAN CULTURAL CENTER Phase 2 Improvements MACC Advisor y Board Update Heidi Tse Capital Delivery Project Manager April 1, 2026 Milestones Reached Certificate of Occupancy Substantial Completion March 4, 2026 February 19, 2026 Programs Begin Parking Lot Opens Late April May 1 Re-Opening Celebrations June 6 Waterloo Greenway Phase II The Confluence opening June 6 Drone Footage December 2026 https://www.austintexas.gov/parks/projects/emma-s- barrientos-mexican-american-cultural-center-phase-2- improvements Questions ? Square Foot Analysis