Item 4. Update on the Phase 2 Construction Project — original pdf
Backup

Emma S. Barrientos Mexican American Cultural Center Phase 2 Improvements Project Update September 10, 2025 Heidi Tse, Capital Delivery Project Manager PROJECT TIMELINE: ESB MACC Groundbreaking for Phase 2 Improvements / Move-Out Began– 12/10/22. • • Parking Lot Closure – 3/10/23. • Contractor Mobilization/Pre-construction Inspections – Began 3/11/23. • Permitting (Site) – Approved on 7/25/23. • Bidding & Negotiation (GMP1/Site) – Executed contract on 8/28/23. • Construction (Site) – Underway since 8/28/23. • Permitting (Building) – Approved on 3/4/24. • Bidding & Negotiation (GMP2/Building) – Executed contract on 3/7/24. • Construction (Site + Building) – Currently underway. • AIPP ESB-MACC Phase 2 – Artist(s) selection approval by Austin City Council on 8/29/24 • • Building dry-in – Process of ensuring the building envelope is weather sealed is expected September. Topping Out – Topmost structural beam was lifted into place on 9/11/24. CONSTRUCTION PROGRESS: • • • • Zocalo paver installation 90% complete. Landscape installation 75% complete. Site furnishings bike racks and benches installation in progress. Interior ceiling, flooring and lighting installation 90% complete. • Plumbing fixtures installation 75% complete. • Kitchen appliances installed. • Window shades and acoustical panels installation 80%. • Data, and security installation in progress. ANNOUNCEMENTS: • Katherine Telley and Ruben Esquivel, the awarded artists for ESB MACC Phase 2, Art in Public Places (AIPP) project are working on the design of their titled piece, Arcos de Conexión. Please visit AIPP website for more announcements. • Concrete pours will continue. Work hours will adhere to the City’s noise ordinance. Ordinance information can be found here. • The Confluence, a separate public/private partnership project is using the parking lot as construction access point for the east side of the creek delta. Improvements are also being made to provide connection between the MACC and The Confluence at the west edge of the parking lot. Additional information can be found here. • Drone video illustrating ESB MACC site work can be found here. SCHEDULED MILESTONES: • Construction began – August 28, 2023 • Anticipated completion of all major construction activity – September 2025 • Anticipated reopening – November 1, 2025 Please note that as in any construction project, schedules are projected as accurately as possible, but all dates are subject to change due to the nature of construction and weather. For information on ESB MACC programs and staff relocations during construction, visit the MACC webpage: www.austintexas.gov/department/emma-s-barrientos-mexican-american-cultural-center For project updates, visit the project website: www.austintexas.gov/MaccPhase2 Zocalo: Pavers 90% complete. Auditorium: Dry Garden Building Addition: Interior lighting for conference room installed. Building Addition: Dance studio flooring protected and acoustical panels installed. Site: Bike racks installation in progress