Mexican American Cultural Center Advisory BoardAug. 6, 2025

Item 3. Update on the Phase 2 Construction Project — original pdf

Backup
Thumbnail of the first page of the PDF
Page 1 of 6 pages

Emma S. Barrientos Mexican American Cultural Center Phase 2 Improvements Project Update August 6, 2025 Heidi Tse, Capital Delivery Project Manager PROJECT TIMELINE: ESB MACC Groundbreaking for Phase 2 Improvements / Move-Out Began– 12/10/22. • • Parking Lot Closure – 3/10/23. • Contractor Mobilization/Pre-construction Inspections – Began 3/11/23. • Permitting (Site) – Approved on 7/25/23. • Bidding & Negotiation (GMP1/Site) – Executed contract on 8/28/23. • Construction (Site) – Underway since 8/28/23. • Permitting (Building) – Approved on 3/4/24. • Bidding & Negotiation (GMP2/Building) – Executed contract on 3/7/24. • Construction (Site + Building) – Currently underway. • AIPP ESB-MACC Phase 2 – Artist(s) selection approval by Austin City Council on 8/29/24 • • Building dry-in – Process of ensuring the building envelope is weather sealed is expected August. Topping Out – Topmost structural beam was lifted into place on 9/11/24. CONSTRUCTION PROGRESS: • • • Zocalo paver installation 80% complete. Sculpture garden granite path in progress. Landscape installation underway. • Windows & doors being tested for water seal and airtightness. • Dividing partitions installed in classrooms. • • Interior flooring installation in progress. Interior shelving and cabinetry installed. • Exterior and interior lighting installation in progress. ANNOUNCEMENTS: • Large hauls and concrete pours will continue. Work hours will adhere to the City’s noise ordinance. Ordinance information can be found here. • The Confluence, a separate public/private partnership project has increased activities at the ESB MACC. The parking lot is the construction access point for the east side of the creek delta. There are trail detours because of the trail enhancements. Additional information can be found here. • The MACC round-about and driveways continue to experience elevated traffic and congestion due to the volume of work in the area and by other developers. Please exercise caution in this district and check for road closures. • Drone video illustrating ESB MACC site work can be found here. SCHEDULED MILESTONES: • Construction began – August 28, 2023 • Anticipated completion of all major construction activity – Late Summer 2025 • Anticipated reopening – November 1, 2025 Please note that as in any construction project, schedules are projected as accurately as possible, but all dates are subject to change due to the nature of construction and weather. For information on ESB MACC programs and staff relocations during construction, visit the MACC webpage: www.austintexas.gov/department/emma-s-barrientos-mexican-american-cultural-center For project updates, visit the project website: www.austintexas.gov/MaccPhase2 Zocalo: Paver installation 80% complete. Zocalo: Planting in progress. Sculpture Garden: Granite walking path in progress. Snake Path: Plantings in progress. Building Addition: Operable dividing partitions installed in classrooms. Building Addition: Dance studio flooring complete. Building Addition: Classroom millwork installed. Existing Building: Exterior lighting replacement complete.