Mexican American Cultural Center Advisory BoardJune 2, 2021

Backup — original pdf

Backup
Thumbnail of the first page of the PDF
Page 1 of 1 page

Emma S. Barrientos Mexican American Cultural Center Phase 2 Improvements June 2021 Updates Heidi Tse, PWD - Capital Delivery Project Manager o Request to increase PSA Authority for City Council’s approval on 6/3/21 Increase from $2.5M to $3.9M to cover CD - Post Construction Phase Services o Virtual (1.5 day) Charrette was held on May 13th & 17th utilizing Miro Board o In-Person on site (2 half days) Charrette will be held on June 7th & 8th. o Geotechnical Engineering on site boring will be targeted for June 9-19th pending weather conditions o Pink Consulting Kick-Off Meeting on May 27 for Community Outreach planning for Schematic Design o Three Community Meetings targeting August (Day, Night, & Saturday) o Combining Small Groups o Methods