20201104-002a: Country Club Creek West at Roy G. Guerrero Park Update — original pdf
Backup
Country Club Creek West at Roy G Guerrero Park Environmental Commission November 4, 2020 Janna Renfro, P.E. Project Sponsor Watershed Protection Department 1 Project Area Roy G. Guerrero Colorado River Metro Park • 363 acres • Constructed drainage channel – Country Club West • Original drainage • channel – Country Club East Improvements constructed in 2010 2 Erosion Damage • 2015 Floods • Severe erosion created a shorter path to the river. • Pedestrian bridge collapsed • May 2015 ‐ December 2017: Erosion damaged ~1500 feet (5 acres) of drainage channel • 100s of trees lost • 2500 dump truck loads of sand and soil (~37,000 cubic yards) 3 Permanent Solution • ~2,000 linear feet of channel stabilization • Three concrete “drop structures” • Natural channel between structures • Bridge over middle structure above 500‐ year flood elevation 4 Temporary Repairs • Project No. 1 • 2017 • Protect Ballfields Interim Project № 1 Permanent Project 5 Temporary Repairs • Project No. 2: • 2018 • Stop headcut from moving upstream Interim Project № 2 Permanent Project 6 2019 – 2020 Update Items • Erosion Progresses • Three New Temporary Repair Projects • Emergency Affidavit • 60% Design Deliverable • Updated Construction Cost Estimate • Schedule 7 Temporary Repairs • Project No. 3: • 2019‐20 • Protect 54” Active Wastewater Line Interim Project № 3 Permanent Project 8 Temporary Repairs • Project No. 4: • 2020 • Protect Park Road Interim Project № 4 Permanent Project 9 Temporary Repairs • Project No. 5: • 2020 • Repair failed temporary headcut stabilization Interim Project № 5 Permanent Project 10 Emergency Affidavit • Summer 2019: ◦ New LiDAR ◦ Progression of erosion ◦ Continuing vulnerability of temporary repairs ◦ Need for additional temporary measures • Fall 2019 ◦ Emergency affidavit ◦ Expedited bid process 11 60% Design & Cost Estimate • 60% Design – Received Spring 2020 • Construction Cost Estimate — $25M ◦ Why? ◦ How? 12 Project Schedule Complete Design Bid Begin Construction Complete Construction 13 14 Trail Connectivity 15 Physical Modeling • Conditions are unique and challenging • High consequence of failure requires more certainty • Improve drop structure design • Determine stable channel configuration 16 Model Findings 9 Revise channel alignment 9 Maximize width 9 Structure modifications Do nothing? • Headcut will continue to move upstream. • High confidence of threats upstream • Increasingly expensive project Wickersham ‐ BEFORE Current Headcut Location Wickersham ‐ AFTER 18