Arts CommissionMay 18, 2020

Art in Public Places Rosewood Design Packet — original pdf

Backup
Thumbnail of the first page of the PDF
Page 1 of 14 pages

Rosewood Neighborhood Park - AIPP Project Budget Summary (Final Revised 5-12-2020) Project Mosaic Tech/Lighting Studio Rental (Muzacz + Polis) $ 2,400.00 Costs Insurance Community Engagement Photography for Mosaic $ 200.00 $ 576.00 $ 1,250.00 Artist Fee (20% of commission) $ 8,800.00 Materials Mosaic Lighting Framing Control Electrical Labor CNC Programming Framing Mosaic Tile Placement Mosaic Tile Adhesion Installation ($4320 total) $ 4,302.00 $ 3,271.00 $ 4,329.00 $ 1,599.00 $ 1,457.00 $ 896.00 $ 2,880.00 $ 4,500.00 $ 900.00 $ 1,440.00 $ 2,160.00 $ 2,160.00 Subtotal $ 13,226.00 $ 18,909.00 $ 10,985.00 $ 43,120.00 Artist Contingency (2% of Artist Budget) Additional AIPP Program Contingency (3% of Artist Budget) $ 880.00 $ 1,320.00 $ 44,000.00 Total Artist Budget