Electric Utility Commission Homepage

RSS feed for this page

Feb. 14, 2022

Item 18: February 2021 Winter Storms After Action Report Follow-up re Load Shed and Circuit Sectionalizing original pdf

Thumbnail of the first page of the PDF
Page 1 of 9 pages

Item 18 February 2021 Winter Storms After-Action Report Follow-up Actions Pertaining to ERCOT-Mandated Load Shed Tom Pierpoint Vice President, Electric System Engineering & Technical Services February 14, 2022 ©2022 Austin Energy Topics • Austin Energy February 2021 Winter Storms After-Action Report • Impact of ERCOT-Mandated Load Shed • Circuit Reconfiguration and Sectionalizing • Key Actions to Add Circuits and Further Capacity to Manual Load Shed • After-Action Report Status of Follow-up Actions • Questions & Comments 2 ERCOT must mandate Load Shed at any time, frequency, duration or level to stabilize the Texas Electric Grid Austin Energy has a broad strategy to meet ERCOT- Mandated Load Shed 3 Impact of ERCOT-Mandated Load Shed 4 Electric Circuit Portfolio for ERCOT-Mandated Load Shed Category of Circuit Manual Load Shed Characteristics of Circuit Can be used for cycling Under Frequency Load Shed (UFLS) Required by ERCOT to be reserved and pre-programmed Can be used for cycling in specific situations Dedicated / Industrial Circuits and customers that cannot be cycled Customer-side curtailment instead of power interruption Downtown Underground Network Circuits likely damaged or destroyed by cycling Customer-side curtailment instead of power interruption Critical Load – Life Sustaining No life-sustaining facilities lost power 5 Circuit Reconfiguration & Sectionalizing Each situation must be carefully evaluated by skilled engineers and field technicians for feasibility. Streets & Buildings Other Utility Infrastructure Major Electric Lines Detailed Electric Topology Some factors to consider • Sectionalizing originally implemented for reliability, not load shed • Location of critical load customers • Pole loading, circuit density and 3rd party attachments • Affordability (dependent on the situation) Load Shed Sectionalizing Pilot • Analyzing 7 circuits for manual intervention • More circuits would require automation Primary challenges of large-scale Sectionalizing • Critical load customers must be at head end of circuit • Changes to Control Center computer • Build-out of two-way wireless communications system • New equipment and modify existing equipment on poles • At least a 3–5-year timeline 6 Key Actions to Add Circuits and Further Capacity to Manual Load Shed Category Manual Load Shed Under Frequency Load Shed Dedicated / Industrial Downtown Underground Network Critical Load – Life Sustaining Additional Flexibility to Reassign Circuits Industrial Curtailment Program Curtailment for Commercial Reconfigured 3 Critical Load Circuits 7 After-Action Report Status of Follow-up Actions 8 Questions and Comments Thank You! 9

Scraped at: Feb. 11, 2022, 3 p.m.
Feb. 14, 2022

Items 2-14: Draft RCAs original pdf

Thumbnail of the first page of the PDF
Page 1 of 18 pages

Item 2 Posting Language ..Title Authorize an amendment to a contract with Nalco Company LLC d/b/a Nalco Company for continued specialty chemical water treatment services, to increase the amount by $3,500,250 and to extend the term by one year, for a revised total contract amount not to exceed $14,687,500. (Note: This contract was reviewed for subcontracting opportunities in accordance with City Code Chapter 2- 9C Minority Owned and Women Owned Business Enterprise Procurement Program. For the goods and services required for this contract, there were insufficient subcontracting opportunities; therefore, no subcontracting goals were established). ..Body Lead Department Financial Services Department. Client Department(s) Austin Energy, Austin Convention Center Department, Austin Public Library, Aviation, Building Services Department, Parks and Recreation Department. Fiscal Note Funding in the amount of $2,333,500 is available in the Fiscal Year 2021-2022 Operating Budgets of various City departments. Funding for the remaining contract term is contingent upon available funding in future budgets. Purchasing Language: Contract Amendment. Prior Council Action: February 2, 2017 – Council approved the original contract, item 28, on a 10-0 vote with Council Member Casar off the dais. December 3, 2020 – Council approved an amendment, item 29, on an 11-0 vote. For More Information: Inquiries should be directed to Julia Finn, at 512-322-6060 or Julia.Finn@austintexas.gov. Council Committee, Boards and Commission Action: February 14, 2022 - To be reviewed by the Electric Utility Commission. Additional Backup Information: The proposed amendment will provide City departments additional funding for continued specialty chemical water treatment services. These specialty chemicals protect assets such as chilled water loops, power boilers, and condenser water loops. These chemicals are specifically blended and designed to prevent hazardous public health issues and reduce or eliminate corrosion and erosion within the different piping loops located at various City facilities including the power plants, chilled water plants, City office buildings, as well as the airport. The original funding request was based on a five-year forecast for several City departments. This request will provide continued services until a new contract is established. ..Strategic Outcome(s) Strategic Outcome(s): Safety, Government that Works for All, Health and Environment. . Item 3 Posting Language ..Title Authorize an amendment to a contract with SAP America Inc. to provide a continued subscription for talent, performance, and learning management software, to increase the amount by $198,000 and to extend the term by one year, for a revised total contract amount not to exceed $3,146,933. …

Scraped at: Feb. 11, 2022, 3 p.m.
Feb. 14, 2022

Revised Agenda original pdf

Thumbnail of the first page of the PDF
Page 1 of 4 pages

Electric Utility Commission February 14, 2022  6:00 PM Austin Energy Headquarters; 1st Floor; Shudde Fath Conference Room 4815 Mueller Blvd, Austin TX 78723 Some members of the Electric Utility Commission maybe participating by videoconference. The meeting may be viewed online at: http://www.austintexas.gov/page/watch-atxn-live Public comment will be allowed in-person or remotely by telephone. Speakers may only register to speak on an item once either in-person or remotely and will be allowed up to three minutes to provide their comments. Registration no later than noon the day before the meeting is required for remote participation. To register contact Robin Otto at Robin.Otto@austinenergy.com or 512-322-6254. REVISED AGENDA Members: Marty Hopkins, Chair (Casar) Dave Tuttle, Vice Chair (Alter) Marshall Bowen (Kelly) Randy Chapman (Pool) Cary Ferchill (Adler) Erik Funkhouser (Fuentes) Karen Hadden (Kitchen) Makenna Jonker (Harper- Madison) Cyrus Reed (Tovo) Kay Trostle (Ellis) Vacancy (Renteria) For more information, please visit: www.austintexas.gov/euc Reading and Action on Consent Agenda: Items 2-14 may be acted upon by one motion. No separate discussion or action on any of the items is necessary unless desired by a Commissioner. CALL MEETING TO ORDER CITIZEN COMMUNICATION: GENERAL Speaker must be present and will be allowed up to three minutes to provide their comments. 1. APPROVAL OF MINUTES – Approve minutes of the November 19, 2021 meeting. NEW BUSINESS – CONSENT ( ) = Target Council Meeting Date; [ ] = RCA Type 2. (3/3) [Purchasing – Multi-Departmental; AE’s portion approximately $12.7M] Authorize an amendment to a contract with Nalco Company LLC d/b/a Nalco Company for continued specialty chemical water treatment services, to increase the amount by $3,500,250 and to extend the term by one year, for a revised total contract amount not to exceed $14,687,500. 3. (3/3) [Purchasing] Authorize an amendment to a contract with SAP America Inc. to provide a continued subscription for talent, performance, and learning management software, to increase the amount by $198,000 and to extend the term by one year, for a revised total contract amount not to exceed $3,146,933. 4. (3/3) [Purchasing] Authorize award of a contract with Johnson Controls Inc d/b/a Johnson Controls to provide fire protection and maintenance services, for a term of five years in an amount not to exceed $2,000,000. 5. (3/3) [Purchasing] Authorize negotiation and execution of a multi-term contract with Power Grid Engineering, LLC to provide relay services, for up to five years in an amount not to exceed …

Scraped at: Feb. 12, 2022, 5:30 a.m.
Feb. 14, 2022

Play video original link

Play video

Scraped at: March 1, 2022, 3:30 a.m.
Feb. 14, 2022

Approved Minutes original pdf

Thumbnail of the first page of the PDF
Page 1 of 3 pages

Electric Utility Commission February 14, 2022 Minutes The Electric Utility Commission (EUC) convened a regularly scheduled meeting at Austin Energy Headquarters, with some members attending via videoconference/Webex. Meeting called to order by Chair Hopkins at 6:10 p.m. Also present were Commissioners Chapman, Reed, Jonker, Trostle (v), Hadden (v), Bowen (v), Ferchill (v) and Funkhauser (v). Vice-Chair Tuttle was absent and there is one vacancy. CITIZEN COMMUNICATION: None 1. APPROVAL OF MINUTES – Approve minutes of the November 8, 2021. No action taken. NEW BUSINESS – CONSENT ( ) = Target Council Meeting Date; [ ] = RCA Type Motion (Funkhouser) to recommend Items 2-5, 13; seconded (Chapman); passed on a vote of 8-0, with Vice Chair Tuttle and Commissioner Ferchill absent and one vacancy. Motion (Reed) to recommend Items 6-12; seconded (Jonker); passed on a vote of 8-0, with Vice Chair Tuttle and Commissioner Ferchill absent and one vacancy. Motion (Trostle) to recommend Item 14; seconded (Funkhouser); passed on a vote of 9-0, with Commissioner Ferchill absent and one vacancy. 1. (3/3) [Purchasing – Multi-Departmental; AE’s portion approximately $12.7M] Authorize an amendment to a contract with Nalco Company LLC d/b/a Nalco Company for continued specialty chemical water treatment services, to increase the amount by $3,500,250 and to extend the term by one year, for a revised total contract amount not to exceed $14,687,500. 2. (3/3) [Purchasing] Authorize an amendment to a contract with SAP America Inc. to provide a continued subscription for talent, performance, and learning management software, to increase the amount by $198,000 and to extend the term by one year, for a revised total contract amount not to exceed $3,146,933. 3. (3/3) [Purchasing] Authorize award of a contract with Johnson Controls Inc d/b/a Johnson Controls to provide fire protection and maintenance services, for a term of five years in an amount not to exceed $2,000,000. 4. (3/3) [Purchasing] Authorize negotiation and execution of a multi-term contract with Power Grid Engineering, LLC to provide relay services, for up to five years in an amount not to exceed $6,000,000. 5. (3/3) [Austin Energy](T1) Approve a resolution authorizing the filing of eminent domain proceedings for the acquisition of real property rights consisting of a Temporary Construction Easement containing approximately 4,438 square feet of land, being a part of Lot A-4-1 of the Resubdivision of Lot 4-A of the Resubdivision of Lot A-1 of the Resubdivision of Lot “A”, Tempo North, a …

Scraped at: April 14, 2022, 9:30 p.m.
Jan. 10, 2022

Agenda original pdf

Thumbnail of the first page of the PDF
Page 1 of 3 pages

Electric Utility Commission January 10, 2022  6:00 PM Austin Energy Headquarters; 1st Floor; Shudde Fath Conference Room 4815 Mueller Blvd, Austin TX 78723 (Note: Some Commission members and presenters may be participating by videoconference.) AGENDA Members: Marty Hopkins, Chair (Casar) Dave Tuttle, Vice Chair (Alter) Marshall Bowen (Kelly) Randy Chapman (Pool) Cary Ferchill (Adler) Erik Funkhouser (Fuentes) Karen Hadden (Kitchen) Makenna Jonker (Harper- Madison) Cyrus Reed (Tovo) Kay Trostle (Ellis) Vacancy (Renteria) For more information, please visit: www.austintexas.gov/euc Reading and Action on Consent Agenda: Items 2-19 may be acted upon by one motion. No separate discussion or action on any of the items is necessary unless desired by a Commissioner. CALL MEETING TO ORDER CITIZEN COMMUNICATION: GENERAL Speaker must be present and will be allowed up to three minutes to provide their comments. 1. APPROVAL OF MINUTES – Approve minutes of the November 19, 2021 meeting. NEW BUSINESS – CONSENT ( ) = Target Council Meeting Date; [ ] = RCA Type 2. (1/27) [Purchasing] Authorize negotiation and execution of six contracts to provide weatherization services, with 1st Choice Energy LLC d/b/a 1st Choice Energy, 360 Energy Savers LLC, Conservation Specialists of Austin, LLC, Good Neighbor Management d/b/a City Conservation d/b/a Totally Cool, KL Austin Roofing and Construction d/b/a Green Squads, and McCullough Heating & Air Conditioning Inc d/b/a McCullough Heating & Air Conditioning, each for a term of five years in an amount not to exceed $19,000,000 divided among the contractors. 3. (1/27) [Purchasing] Authorize award of two contracts with KBS Electrical Distributors Inc., a local bidder that offers the City the best combination of contract price and additional economic development opportunities including the employment of residents and increased tax revenues, and Sherman & Reilly to provide bundle stringing blocks in an amount not to exceed $160,000 divided between the contractors. 4. (1/27) [Austin Energy] Authorize negotiation and execution of all documents and instruments necessary or desirable to acquire a permanent Electric Transmission and Distribution Easement consisting of approximately 0.114 acre (4,958 square feet), out of the North Lamar Park Annex, a subdivision in Travis County, Texas, and being a portion of the property located at 9307 N. Lamar Blvd., Austin, Texas 78753, for the Austin Energy Transmission Circuit 811 JL-MC 138kV upgrade project, in an amount not to exceed $323,243, including standard and customary closing costs and fees. 5. (1/27) [Austin Energy] Authorize expenditures for annual renewals …

Scraped at: Jan. 7, 2022, 2 p.m.
Jan. 10, 2022

Item 20: AE HQ Update original pdf

Thumbnail of the first page of the PDF
Page 1 of 8 pages

Item 20 Corporate Headquarters Project Update Robin Cappello Director, Corporate Support Services 01/10/2022 © 2021 Austin Energy Highlights Project Status Project Performance 1 2 3 Schedule and Upcoming Milestones 2 Project Report Project Completion 100% Project Brief The Austin Energy Corporate Headquarters Project is largely complete with all major construction milestones achieved to position the Utility to commence operations within the facility. The Public Private Partnership real estate development model proved effective in delivering a high quality and cost-effective vertical construction project from inception through completion. The project goals were LEED Gold 4-Star minimum standards. Project is on target to achieve LEED Platinum /AEGB 5-Star accreditation. The project goals were WELL Silver building standards. Project is on target to achieve WELL Gold accreditation. Features:  LED Lighting  Smoke-Free Campus  Ergonomic Furniture  UV Air filtration MERV-13 (hospital grade) 3 Project Report Austin Energy’s Corporate Headquarters modern and sustainable design is a vibrant new addition to the Mueller Development 4 Project Report Iconic Colorado River path embedded in the flooring of main lobby of the headquarters as a historical milestone reference for Austin Energy Prominent Staircase is a focal point of the building providing connections throughout the facility. It promotes ‘chance meetings’ and opportunities to engage Community Courtyard hosts amenities which allow for linkages to the outdoors and a variety of different meet-up offerings 5 Project Performance • Total Project Cost = $142.5M • Change Order actuals = 1.43% City Council Authority $150M Change Order Goals Less than 5% Original Substantial Completion Date (per PSA) 4/5/21 Project Closing Date Goal Winter 2021 • Actual Substantial Completion Date - 4/5/21 • Actual closing date - 4/8/21 6 Schedule and Upcoming Milestones • All AE teams completed move activities in October 2021 • *AE fully operational at Corporate Headquarters November 1, 2021 • Workplace reintegration for AE January 31, 2022 *AE operated in a ‘Stay Home, Stay Safe’ workplace readiness posture 7 Q&A ©2019 Austin Energy. All rights reserved. Austin Energy and the Austin Energy logo and combinations thereof are trademarks of Austin Energy, the electric department of the City of Austin, Texas. Other names are for informational purposes only and may be trademarks of their respective owners.

Scraped at: Jan. 7, 2022, 2 p.m.
Jan. 10, 2022

Item 24: Council Action Report original pdf

Thumbnail of the first page of the PDF
Page 1 of 2 pages

Item 24 EUC Report re Council Action January 10, 2022 Items below recommended by EUC November 8; Council approved on date indicated in parenthesis. 2. (11/18) [Purchasing] Authorize award of a contract with KBS Electrical Distributors Inc. to provide a station service voltage transformer in an amount not to exceed $67,000. 3. (11/18) [Purchasing] Ratify a contract with Control Components Inc, to provide an intermediate pressure drum control valve and spare parts, in the amount of $75,400. 4. (11/18) [Capital Contracting] Authorize negotiation and execution of a construction contract with MasTec North America, Inc., for Underground Electrical Civil Construction Indefinite Delivery/ Indefinite Quantity contract in the amount of $24,000,000 for an initial 2-year term, with four 1-year extensions of $12,000,000, for a total contract amount not to exceed $72,000,000. 5. (12/2) [Purchasing Multi Departmental; AE’s estimated portion is $6.3M] Authorize award of two contracts with Community Trucking LLC, and Green Dream International d/b/a GDI, to provide flexible base, surface rock and 3x5 rock, each for a term of five years for total contract amounts not to exceed $7,570,000, divided between the contractors. 6. (12/2) [Purchasing] Authorize an amendment to a contract with Texas Electric Cooperatives, for the continued purchase of electric meters for use throughout the Austin Energy service area, to increase the amount by $10,000,000 and to extend the term by 18 months, for a revised total contract amount not to exceed $40,000,000. 7. (12/2) [Purchasing] Ratify a contract with Techline Inc. to provide distribution steel poles, in an amount of $750,000. 8. (12/2) [Purchasing] Authorize additional expenditures to a contract with Techline Inc., to continue providing distribution steel poles, in the amount of $3,750,000 for a revised total contract amount not to exceed $4,500,000. 9. (12/2) [Purchasing] Authorize negotiation and execution of a cooperative contract with Accenture LLP, to provide implementation and managed services, related maintenance and support for the Sitecore web content management solution, for a term of three years in an amount not to exceed $2,306,000. 10. (12/2) [Purchasing] Authorize an amendment to a contract with GE Energy Management Services Inc, for continued maintenance and support of the GE Smallworld Geographic Information Systems software suite, to increase the amount by $399,325 and to extend the term by one year, for a revised total contract amount not to exceed $5,716,354. 11. (12/2) [Purchasing] Authorize an amendment to a contract with Eaton Corporation, for prevention maintenance and corrective …

Scraped at: Jan. 7, 2022, 2 p.m.
Jan. 10, 2022

Items 2-19: Draft RCAs original pdf

Thumbnail of the first page of the PDF
Page 1 of 33 pages

Item 2 Posting Language ..Title Authorize negotiation and execution of six contracts to provide weatherization services, with 1st Choice Energy LLC d/b/a 1st Choice Energy, 360 Energy Savers LLC, Conservation Specialists of Austin, LLC, Good Neighbor Management d/b/a City Conservation d/b/a Totally Cool, KL Austin Roofing and Construction d/b/a Green Squads, and McCullough Heating & Air Conditioning Inc d/b/a McCullough Heating & Air Conditioning, each for a term of five years in an amount not to exceed $19,000,000 divided among the contractors. (Note: This solicitation was reviewed for subcontracting opportunities in accordance with City Code Chapter 2-9C Minority Owned and Women Owned Business Enterprise Procurement Program. For the goods and services required for this solicitation, there were no subcontracting opportunities; therefore, no subcontracting goals were established). ..Body Lead Department Financial Services Department. Client Department(s) Austin Energy. Fiscal Note Funding in the amount of $2,533,333 is available in the Fiscal Year 2021-2022 Operating Budget of Austin Energy. Funding for the remaining contract terms is contingent upon available funding in future budgets. Purchasing Language: The Financial Services Department issued a Request for Qualification Statements (RFQS) 1100 EAL4000 for these goods and services. The solicitation issued on June 7, 2021 and it closed on July 20, 2021. Of the eight offers received, the recommended contractors submitted the best evaluated responsive offers. A complete solicitation package, including a log of offers received, is available for viewing on the City’s Financial Services website, Austin Finance Online. Link: Solicitation Documents . Prior Council Action: For More Information: Respondents to this solicitation, and their representatives, shall continue to direct inquiries to the solicitation’s Authorized Contact Person: Liz Lock, at 512-322-6251 or Liz.Lock@austintexas.gov. Council Committee, Boards and Commission Action: January 10, 2022 - To be reviewed by the Electric Utilities Commission. Additional Backup Information: These contracts will provide weatherization services for Austin Energy qualifying customers. Austin Energy’s weatherization program provides home energy improvements to customers with low to moderate incomes living in single family homes, duplexes, triplexes, fourplexes, and manufactured homes. The provided improvements reduce customers’ energy costs while creating a more comfortable and safe living environment. These services may include sealing the building structure to address air infiltration, duct repair or replacement, installing attic insulation, solar screens, smoke detectors, carbon monoxide detectors, high efficiency lighting, air conditioning tune ups and smart thermostats. Additional measures may be provided through partnerships with and referrals from Austin Housing Repair Coalition …

Scraped at: Jan. 7, 2022, 2 p.m.
Nov. 8, 2021

Agenda original pdf

Thumbnail of the first page of the PDF
Page 1 of 3 pages

Electric Utility Commission November 8, 2021  6:00 PM Austin Energy Headquarters; 1st Floor; Shudde Fath Conference Room 4815 Mueller Blvd, Austin TX 78723 (Note: Some members of the Electric Utility Commission may be participating by videoconference.) AGENDA Members: Marty Hopkins, Chair (Casar) Dave Tuttle, Vice Chair (Alter) Marshall Bowen (Kelly) Randy Chapman (Pool) Cary Ferchill (Adler) Erik Funkhouser (Fuentes) Karen Hadden (Kitchen) Cyrus Reed (Tovo) Kay Trostle (Ellis) Vacancy (Harper-Madison) Vacancy (Renteria) For more information, please visit: www.austintexas.gov/euc Reading and Action on Consent Agenda: Items 2-17 may be acted upon by one motion. No separate discussion or action on any of the items is necessary unless desired by a Commissioner. CALL MEETING TO ORDER CITIZEN COMMUNICATION: GENERAL Speaker must be present and will be allowed up to three minutes to provide their comments. 1. APPROVAL OF MINUTES – Approve minutes of the August 19, 2021 special-called meeting. NEW BUSINESS – CONSENT ( ) = Target Council Meeting Date; [ ] = RCA Type 2. (11/18) [Purchasing] Authorize award of a contract with KBS Electrical Distributors Inc. to provide a station service voltage transformer in an amount not to exceed $67,000. 3. (11/18) [Purchasing] Ratify a contract with Control Components Inc, to provide an intermediate pressure drum control valve and spare parts, in the amount of $75,400. 4. (11/18) [Capital Contracting] Authorize negotiation and execution of a construction contract with MasTec North America, Inc., for Underground Electrical Civil Construction Indefinite Delivery/ Indefinite Quantity contract in the amount of $24,000,000 for an initial 2-year term, with four 1-year extensions of $12,000,000, for a total contract amount not to exceed $72,000,000. 5. (12/2) [Purchasing Multi Departmental; AE’s estimated portion is $6.3M] Authorize award of two contracts with Community Trucking LLC, and Green Dream International d/b/a GDI, to provide flexible base, surface rock and 3x5 rock, each for a term of five years for total contract amounts not to exceed $7,570,000, divided between the contractors. 6. (12/2) [Purchasing] Authorize an amendment to a contract with Texas Electric Cooperatives, for the continued purchase of electric meters for use throughout the Austin Energy service area, to increase the amount by $10,000,000 and to extend the term by 18 months, for a revised total contract amount not to exceed $40,000,000. 7. (12/2) [Purchasing] Ratify a contract with Techline Inc. to provide distribution steel poles, in an amount of $750,000. 8. (12/2) [Purchasing] Authorize additional expenditures to …

Scraped at: Nov. 5, 2021, 7 p.m.
Nov. 8, 2021

Item 18: Generation Portfolio Update original pdf

Thumbnail of the first page of the PDF
Page 1 of 9 pages

Item 18 Generation Portfolio Update Fayette Power Project, Decker Unit 2 and Nacogdoches Power Project Pat Sweeney Vice President, Power Production Nov. 8, 2021 © 2021 Austin Energy Announcement Highlights • Negotiations stall over Fayette Power Project • Decker 2 steam unit to shut down in March 2022 • Nacogdoches biomass plant to be available year-round Fayette Power Project Photo courtesy LCRA Decker Creek Power Station Nacogdoches Power Project 2 Negotiations stall over Fayette Power Project (FPP) • Background: Austin Energy co-owns FPP with LCRA; Austin Energy’s portion is 50% of two of the three units; LCRA manages the plant. • Joint ownership agreement does not set out how one party can retire only its share of the project. • Unable to reach terms that would allow Austin Energy to shut down its share. 3 Negotiations stall over Fayette Power Project • What’s next? • Austin Energy will continue to run its portion of FPP but will minimize scheduled output using REACH • The REACH strategy considers the cost of carbon in utility’s offers to sell generation from FPP. • Continue to negotiate with LCRA to retire Austin Energy’s share of FPP. 4 Decker Steam Unit 2 to Close March 2022 City Council approved closure in 2017 Age Less Efficient Lower Carbon Emissions Increasing difficult to maintain, secure replacement parts and technical expertise Requires more natural gas per megawatt hour of power compared to newer, more efficient units Part of comprehensive resource plan and commitment to lower carbon footprint 5 Decker Steam Unit 2 to Close March 2022 City Council approved closure in 2017 • Notice of Suspension of Operations (NSO) to ERCOT • Required at least 150 days prior to anticipated retirement date. • Effective retirement date: March 31, 2022. • If ERCOT determines unit needs to continue operating, it can pursue a Reliability Must-Run (RMR) commitment with Austin Energy. • What’s next? • Decker’s four 50 MW gas turbines continue to be available and can be quickly dispatched when needed. 6 Nacogdoches Biomass Plant Available Year-Round • Background: • Plant powered by wood waste fuel. • Previously under “seasonable mothball” status, meaning it was made available to run only during high energy demand summer months. • Utility purchased plant in 2019. • Purchasing the plant saved the utility ~$275M in additional costs over the remaining term of a previous agreement. • Improved operations + current market conditions = …

Scraped at: Nov. 5, 2021, 7 p.m.
Nov. 8, 2021

Item 20: Quarterly Operations Rpt original pdf

Thumbnail of the first page of the PDF
Page 1 of 14 pages

Item 20 Austin Energy Operational Update Q4 FY21 Sidney Jackson Chief Operating Officer, Austin Energy November 2021 © 2018 Austin Energy 1 Austin Energy Operational Update Discussion Topics Performance Carbon Footprint On-Site Energy Resources Future State 2 Austin Energy Operational Update Performance 3 Commercial Availability & Start Success Commercial Availability Generation Resource Target Seasonal Commercial % Availability Commercial Availability Actuals (%) Q3 FY21 AVG Q4 FY21 AVG 94 64 90 87 96 95 99 100 * 95 95 97 100 Decker Steam Units Sand Hill Combined Cycle Fayette Units South Texas Project Start Success Commercial Availability values reflect maintenance or refueling outages typical for this period Start Success Target(%) Start Success Actuals (%) Q4 FY21 AVG Q3 FY21 AVG Simple Cycle Start Success 99 100 100 4 Net Generation and Load Analysis FY 2021 Q4 Power Generation Cost by Fuel Type CONSUMPTION VS. GENERATION (MWH) Nuclear Coal NG Renewable 7% 4% 16% 45% 28% Nuclear Coal NG Renewable Biomass *Costs include fuel for generation, fuel transportation, renewable Power purchases agreements Historical FY21 Q4 System Peak Demand (MW) G E N E R A T I O N L O A D RENEWABLE POWER AS PERCENT OF CONSUMPTION 1,743,775 662,300 1,132,501 919,566 Non-Renewable 58% 4,181,418 Renewable 42% 2,900 2,850 2,800 2,750 2,700 2,650 2,600 2,550 2,500 2018 2019 2020 2021 This information is unaudited and should be read in conjunction with the audited Comprehensive Financial Reports for the City of Austin, when published on 5 System Reliability CAIDIs w/o MED CAIDI = Customer Average Interruption Duration Index Average time to restore service. SAIDI = System Average Interruption Duration Index Total duration of interruptions for the average customer, during a period of time. SAIFI = System Average Interruption Frequency Index How often the average customer experiences a sustain interruption, over a period of time. MED = Major Event Days 65 60 55 50 45 40 I F O N O T A R U D L A T O T I S N O T P U R R E T N I 55.96 45.50 61.39 45.50 82.29 68.51 0.68 0.57 E R O T S E R O T E M T I . G V A I E C V R E S 90 85 80 75 70 65 60 0.75 0.7 0.65 0.6 0.55 0.5 0.45 F O R E B M U N . G V A R …

Scraped at: Nov. 5, 2021, 7 p.m.
Nov. 8, 2021

item 21: Quarterly Financial Rpt original pdf

Thumbnail of the first page of the PDF
Page 1 of 34 pages

Item 21 Austin Energy Quarterly Financial Report 4th Quarter FY 2021 (July - September) Mark Dombroski Chief Financial Officer November 8, 2021 © 2018 Austin Energy Disclaimer Certain information set forth in this presentation contains forecasted financial information. Forecasts necessarily involve known and unknown risks and uncertainties, which may cause actual performance and financial results in future periods to differ materially from any projections of future performance. Although the forecasted financial information contained in this presentation is based upon what Austin Energy management believes are reasonable assumptions, there can be no assurance that forecasted financial information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such forecasts. In addition, this presentation contains unaudited information and should be read in conjunction with the audited Annual Comprehensive Financial Reports for the City of Austin, which was published on March 18, 2021: https://assets.austintexas.gov/financeonline/downloads/comprehensive_annual_financial_report/comprehensi ve_annual_financial_report_2020.pdf 2 QUARTERLY Financial Report Agenda Executive Summary Financial Policy Compliance Financial Performance Measures Actual to Budget Analysis Financial Statements Market and Industry Analyses 3 Austin Energy Quarterly Financial Report Executive Summary 4 Executive Summary Generally compliant with all financial policies. Contingency and Capital Reserve balances below minimums but total cash above minimum of $457m. $ 1,287 Million Revenues Operating revenues at September are 9% under budget due to decreased Power Supply Revenue due to the February winter storm as well as decreased Base revenue. Balance sheet is liquid and adequately capitalized. Working Capital decreased $72M primarily due to funding CIP and decreased base revenue. Generally meeting financial metrics supporting AA credit rating. $937 Million Expenses Operating expenses are 10% under budget due to lower Power Supply costs due to the February winter storm. Market competitiveness – System average rates remain consistent at 2.5% below state average for CY 2020. This information is unaudited and should be read in conjunction with the audited Comprehensive Financial Reports for the City of Austin, when published on https://assets.austintexas.gov/financeonline/downloads/comprehensive_annual_financial_report/comprehensive_annual_financial_report_2020.pdf 5 Austin Energy Quarterly Financial Report Financial Policy Compliance 6 Financial Policy Compliance Financial policies are memorialized and adopted by ordinance each year during the budgeting process Compliance Debt Reserves Operating Non-Compliance Debt Policies Reserves Policies Operating Policies Partial Compliance Partial Compliance Full Compliance Debt Service Coverage 2.0x at September Contingency and Capital Reserve balance below minimums but total cash above minimum of $457m This information is unaudited and should be read in conjunction with the …

Scraped at: Nov. 5, 2021, 7 p.m.
Nov. 8, 2021

Item 22: Draft Recommendation re FPP Resource Plan Working Group original pdf

Thumbnail of the first page of the PDF
Page 1 of 1 page

Draft Resolution/Recommendation for November 8, 2021 EUC Item 22 Whereas the Austin City Council unanimously approved the 2030 Austin Energy Generation Plan in March of 2020, which commits Austin Energy to a zero-carbon goal by 2035; Whereas a key strategy of the 2030 Plan, as well as previous plans such as the 2014 and 2017 Generation Plans, was to commit Austin Energy to cease the burning of coal at the portion of the Fayette Coal Plant owned by Austin Energy by the end of 2022: Whereas Austin Energy has been working on negotiating a solution with the Lower Colorado River Authority, which co-own the plant for several years; Whereas Austin Energy, after consulting with City Council, officially announced on November 1st, 2021 that it had been unable to reach a reasonable and beneficial agreement with LCRA on how to assure retirement of either one unit at Fayette, or a virtual retirement of the approximately 600 MWs of coal owned by Austin Energy by the end of 2022; Whereas emissions of carbon dioxide from the Fayette Power Plant account for approximately 80% of the emissions controlled by Austin Energy and there is no way to meet the goals of the Austin Energy 2030 Resource Plan without ending our use of coal; Therefore, Resolved, the Electric Utility Commission forms a Fayette Power Plant Resource Plan Working Group that will collaborate with Austin Energy to explore options for reducing and ending our use of coal as soon as possible, including:  Continued negotiations with the LCRA to either shut down a unit at Fayette, or virtually shut down the equivalent amount of coal-fired power plants through running the unit less by the end of 2022, or another date in the near future, such as 2023 or 2024;  Expanded use of REACH to bid into the market at a higher price, and therefore reduce the use of coal;  Expansion of zero-carbon resources such as solar and storage at or near the Fayette plant to help in the transition away from coal sooner. Resolved, to the extent the Resource Management Commission also takes a similar action, the EUC working group can meet in person or virtually with members of the RMC to discuss these options, and jointly consider solutions. Resolved, the Fayette Power Plant Resource Plan working group will present recommendations to the full EUC for possible action no later than January 31st, …

Scraped at: Nov. 5, 2021, 7 p.m.
Nov. 8, 2021

Item 23: Proposed 2022 EUC Meeting Schedule original pdf

Thumbnail of the first page of the PDF
Page 1 of 1 page

Item 23 Electric Utility Commission 2022 Meeting Schedule The Electric Utility Commission meets monthly on the second Monday of the month, unless otherwise determined by the Commission. the regular meeting day conflicts with a holiday, the meeting will be held on the following Monday. Meetings are held at 6:00 p.m. in the Shudde Fath Conference Room at Austin Energy HQ, 4815 Mueller Blvd. Changes to the above regarding date, time or location will be noted on meeting agendas. If MEETING DATES January 10, 2022 February 14, 2022 March 21, 2022 April 11, 2022 May 9, 2022 June 13, 2022 July 11, 2022 August 8, 2022 September 12, 2022 October 17, 2022 November 14, 2022 CANCELLED DATES March 14, 2022* October 10, 2022** December 12, 2022*** *AISD/UT/etc. Spring Break **Columbus/Indigineous Peoples Day ***No subsequent Council Meetings in Dec

Scraped at: Nov. 5, 2021, 7 p.m.
Nov. 8, 2021

Items 2 - 17: Draft RCAs original pdf

Thumbnail of the first page of the PDF
Page 1 of 28 pages

Item 2 Posting Language ..Title Authorize award of a contract with KBS Electrical Distributors Inc., to provide a station service voltage transformer, in an amount not to exceed $67,000. (Note: This solicitation was reviewed for subcontracting opportunities in accordance with City Code Chapter 2-9D Minority Owned and Women Owned Business Enterprise Procurement Program. For the goods required for this solicitation, there were no subcontracting opportunities; therefore, no subcontracting goals were established). ..Body Lead Department Purchasing Office. Client Department(s) Austin Energy. Fiscal Note Funding is available in the Fiscal Year 2021-2022 Operating Budget of Austin Energy. Purchasing Language: The Purchasing Office issued an Invitation for Bids (IFB) 1100 PMC1001REBID for this good. The solicitation was issued on July 12, 2021 and closed on July 27, 2021. Of the four offers received, the recommended contractor submitted the lowest responsive offer. A complete solicitation package, including a tabulation of the bids received, is available for viewing on the City’s Financial Services website, Austin Finance Online. Solicitation Documents. Prior Council Action: For More Information: Inquiries should be directed to the City Manager’s Agenda Office, at 512-974-2991 or AgendaOffice@austintexas.gov NOTE: Respondents to this solicitation, and their representatives, shall continue to direct inquiries to the solicitation’s Authorized Contact Persons: Perla Colon at, 512-322-3550 or Perla.Colon@austintexas.gov or Liz Lock at, 512-322-6251 or Liz.Lock@austintexas.gov. Council Committee, Boards and Commission Action: November 8, 2021 - To be reviewed by the Electric Utilities Commission. Additional Backup Information: The contract will provide a 362kV class oil-free station service voltage transformer (SSVT). This transformer is cleaner and environmentally responsible, preventing oil spills throughout the substation and eliminating the need to dispose of oil. The SSVT will be installed inside Austin Energy’s new Cistern substation interconnecting solar energy to Austin Energy’s transmission system. This SSVT will reduce voltage, while increasing the electrical current required for the proper functioning of air conditioning and protective relays. ..Strategic Outcome(s) Strategic Outcome(s): Government that Works for All. Item 3 Posting Language ..Title Ratify a contract with Control Components Inc., to provide an intermediate pressure drum control valve and spare parts, in the amount of $75,400. (Note: This contract is exempt from the City Code Chapter 2-9D Minority Owned and Women Owned Business Enterprise Procurement Program; therefore, no subcontracting goals were established). ..Body Lead Department Purchasing Office. Client Department(s) Austin Energy. Purchasing Language: Ratification. Prior Council Action: Fiscal Note Funding was available in the Fiscal Year 2020-2021 Capital …

Scraped at: Nov. 5, 2021, 7 p.m.
Nov. 8, 2021

Play video original link

Play video

Scraped at: Nov. 11, 2021, 4:30 a.m.
Nov. 8, 2021

Item 19: REACH Update original pdf

Thumbnail of the first page of the PDF
Page 1 of 9 pages

Item 19 2021 REACH Update Electric Utility Commission Briefing Erika Bierschbach VP, Energy Market Operations & Resource Planning November 8, 2021 © 2018 Austin Energy Carbon Reduction - REACH • Reduce Emissions Affordably for Climate Health (“REACH”) incorporates a cost of carbon in the generation dispatch price and reduces generation output during low-margin periods while making resources available for high-margin periods. • Allocate an annual budget amount of approximately 2% of the prior year’s PSA • The savings for 2021 was expected to be 1.29 million metric tons • REACH was designed to reduce the utility’s carbon emissions by 30% or approximately 4 million metric tons between March 26,2020 and December 31,2022. 2 Operational Factors Impacting REACH Goals • Reclaim Pond • Heavy May/June rainstorms caused FPP plant director to declare emergency for low freeboard levels at FPP ponds • Required need to run FPP at elevated levels to help pond's evaporation efforts • Coal Pile Runoff Pond • Heavy rainstorms caused coal pile runoff pond to compromise operational limits • Required need to run FPP at elevated levels to help pond's evaporation efforts • Elevated Coal Pile 3 Operational Factors Impacting REACH Goals (cont.) • Volatile and High Natural Gas Prices • Rising global demand and shifts in supply/demand fundamentals • NYMEX Natural Gas $5.00 - $6.00 range this fall • Higher gas prices require increases in carbon adder to reach targets NYMEX Natural Gas Monthly Settlements $7.00 $6.00 $5.00 $4.00 $3.00 $2.00 $1.00 $- Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 4 Environmental Cost Adder REACH Adder 2021 2.5 1.5 2 1 0 0.5 January February March April May June July August September October November 5 Overall REACH Performance January 1, 2021 – October 31, 2021 Resource Plan Forecast Emissions Economic (Tonnes) Emissions Actual (Tonnes) Emission Reduction (Tonnes) Percentage Below Forecast 4,612,929 4,463,226 3,950,149 662,780 Total Coal 3,592,227 3,475,430 2,962,353 Natural Gas 1,020,702 978,367 978,367 629,874 32,905 14.37% 17.53% 3.22% 6 REACH Performance Explained Emission Reduction Explained - 2021 ) 2 O C ( s e n n o T c i r t e M 5,000,000 4,500,000 4,000,000 3,500,000 3,000,000 2,500,000 2,000,000 1,500,000 1,000,000 500,000 - Projection Reach Impact Outage Impact Model to Market Actual 7 FPP REACH Performance Resource Plan Forecast Emissions Economic (Tonnes) Emissions Actual (Tonnes) Reduction (Tonnes) Cost per Tonne Total FPP1 FPP2 3,592,227 3,475,430 2,962,353 513,077 1,884,255 1,792,651 …

Scraped at: Nov. 11, 2021, 4:30 a.m.
Nov. 8, 2021

Recommendation 20211108-022 Forming a FPP Resource Plan Working Group original pdf

Thumbnail of the first page of the PDF
Page 1 of 2 pages

BOARD/COMMISSION RECOMMENDATION Electric Utility Commission Recommendation No. 20211108-022 FPP Resource Plan Working Group Date: November 8, 2021 Subject: FPP Resource Plan Working Group Motioned: Cyrus Reed Seconded: Cary Ferchill Recommendation: Whereas the Austin City Council unanimously approved the 2030 Austin Energy Generation Plan in March of 2020, which commits Austin Energy to a zero-carbon goal by 2035; Whereas a key strategy of the 2030 Plan, as well as previous plans such as the 2014 and 2017 Generation Plans, was to commit Austin Energy to cease the burning of coal at the portion of the Fayette Coal Plant owned by Austin Energy by the end of 2022: Whereas Austin Energy has been working on negotiating a solution with the Lower Colorado River Authority, which co-own the plant for several years; Whereas Austin Energy, after consulting with City Council, officially announced on November 1st, 2021 that it had been unable to reach a reasonable and beneficial agreement with LCRA on how to assure retirement of either one unit at Fayette, or a virtual retirement of the approximately 600 MWs of coal owned by Austin Energy by the end of 2022; Whereas emissions of carbon dioxide from the Fayette Power Plant account for approximately 80% of the emissions controlled by Austin Energy and there is no way to meet the goals of the Austin Energy 2030 Resource Plan without ending our use of coal; Therefore, Resolved, the Electric Utility Commission forms a Fayette Power Plant Resource Plan Working Group that will collaborate with Austin Energy to explore options for reducing and ending our use of coal as soon as possible, including but not limited to:  Continued negotiations with the LCRA to either shut down a unit at Fayette, or virtually shut down the equivalent amount of coal-fired power plants through running the unit less by the end of 2022, or another date in the near future, such as 2023 or 2024;  Expanded use of REACH to bid into the market at a higher price, and therefore reduce the use of coal;  Expansion of zero-carbon resources such as solar and storage at or near the Fayette plant to help in the transition away from coal sooner. Be it further resolved that the working group provide the EUC with bill impact analysis of each recommendation if available; Resolved, to the extent the Resource Management Commission also takes a similar action, the EUC …

Scraped at: Nov. 16, 2021, 3 p.m.
Sept. 13, 2021

Agenda original pdf

Thumbnail of the first page of the PDF
Page 1 of 3 pages

Electric Utility Commission September 13, 2021  6:00 PM Austin Energy Headquarters; 1st Floor; Shudde Fath Conference Room 4815 Mueller Blvd, Austin TX 78723 AGENDA Members: Marty Hopkins, Chair (Casar) Dave Tuttle, Vice Chair (Alter) Marshall Bowen (Kelly) Randy Chapman (Pool) Cary Ferchill (Adler) Erik Funkhouser (Fuentes) Karen Hadden (Kitchen) Cyrus Reed (Tovo) Kay Trostle (Ellis) Vacancy (Harper-Madison) Vacancy (Renteria) For more information, please visit: www.austintexas.gov/euc Reading and Action on Consent Agenda: Items 2-14 may be acted upon by one motion. No separate discussion or action on any of the items is necessary unless desired by a Commissioner. CALL MEETING TO ORDER CITIZEN COMMUNICATION: GENERAL Speaker must be present and will be allowed up to three minutes to provide their comments. 1. APPROVAL OF MINUTES – Approve minutes of the August 19, 2021 special-called meeting. NEW BUSINESS – CONSENT ( ) = Target Council Meeting Date; [ ] = RCA Type 2. (9/30) [Purchasing Multi Departmental; AE’s estimated portion is $23M] Authorize negotiation and execution of various cooperative contracts during the Fiscal Year 2021-2022, for the purchase of computer, network and other technology hardware, software and related maintenance and technology services, in an amount not to exceed $63,448,196. 3. (9/30) [Austin Energy] Authorize issuance of energy efficiency program rebates by Austin Energy during Fiscal Year 2021-22, in an amount not to exceed $2,700,000 for multifamily energy efficiency rebates and $3,350,000 for commercial and small business energy efficiency rebates, for a total combined amount not to exceed $6,050,000. 4. (9/30) [Capital Contracting] Authorize award and execution of a construction contract with Muniz Concrete & Contracting, Inc, for District Cooling Plant #2 (DCP2) Chemical Storage Addition project in the amount of $593,568.70 plus a $59,356.87 contingency, for a total contract amount not to exceed $652,925.57. 5. (10/14) [Purchasing] Authorize award of contracts with Techline Inc., and Wesco Distribution Inc. D/B/A Hi-Line Utility Supply Co, LLC, to provide streetlight poles and pole parts, each for a term of five years in an amount not to exceed $4,820,000, divided between the contractors. 6. (10/14) [Purchasing] Authorize award of a contract with Enterprise Professional Services, Inc. D/B/A EPSI for landscaping and ground maintenance services, for a term of five years for a total contract amount not to exceed $742,500. 7. (10/14) [Purchasing] Authorize execution of a contract with ErgoFlex Systems, Inc. D/B/A Xybix Systems, Inc, to provide ergonomic workstations and installation for Austin Energy, for …

Scraped at: Sept. 10, 2021, 2:30 p.m.